The investment and development hub of the North Coast
Admin
69 kV Puerto Plata I – Puerto Plata II transmission line upgrade
← Public works

ENERGY · San Felipe de Puerto Plata

69 kV Puerto Plata I – Puerto Plata II transmission line upgrade

Reinforcement of the 69 kV line that powers the province. ETED reported 95% progress on the structures.

Photo: File photo · Mustang Joe, CC0 (Wikimedia Commons)

Under construction

Physical progress95 %
  1. Announced
  2. In tender
  3. Awarded
  4. Under construction
  5. Completed
InvestmentNot published
AgencyDominican Electric Transmission Company (ETED)
Start date—
Delivery—
BeneficiariesMore than 337,000 residents of the northern region
UpdatedNov 21, 2026

Other projects

Follow us and get the newsletter

Puerto Plata tourism, projects, public works and events news every week.